SHAH ALAM, SELANGOR – 16 MARCH 2020: MRCB George Kent Sdn Bhd (MRCBGK), the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be temporary full road closures and traffic diversions on Persiaran Kerjaya, Shah Alam (both Shah Alam and Subang/Kuala Lumpur-bound) from 19 March 2020 to 7 April 2020 (Thursday to Tuesday), 11:00 p.m. to 5:00 a.m.

The temporary full road closures and traffic diversions will occur at the T-junction between Temasya 8 and Caltex, from the T-junction at DRB-Hicom to Jalan Presiden U1/1 and from the T-junction at Temasya Anggun to DRB-Hicom (both Kuala Lumpur/Subang and Shah Alam bound).

The temporary full road closures and traffic diversions are to facilitate pier cap launching works at the road median nearby Temasya 8 and U-Girder launching works at the road median in front of DRB-Hicom, just before Masjid An-Nur Glenmarie, Shah Alam and EON Berhad.

Motorists from Kuala Lumpur/Subang and Shah Alam will be diverted as indicated on the map below:

 

Closure A (19 March 2020 to 21 March 2020) – Pier Cap Launch

 

Closure B (21 March 2020 to 23 March 2020) – U-Girder Launch

 

Closure C (24 March 2020 to 31 March 2020) – U-Girder Launch

 

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

 

For public enquiries, kindly contact the LRT3 hotline at 1 800 18 2585.

 

–END–

 

For media enquiries, please contact:

 

Lim Siew May
Media Manager, PR & Communications
MRCB George Kent Sdn Bhd
03-5033 6857
siewmay.lim@mrcbgk.com

 

 

ABOUT MRCB GEORGE KENT (MRCBGK)

MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4 September 2015 as the Project Delivery Partner (PDP) of Light Rail Transit 3 (LRT3).

On 17 October 2018, the PDP model was replaced with a fixed price contract regime, making MRCB George Kent the contractor.

MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest homegrown railway system specialist in Malaysia.

MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3) PROJECT

The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3.

-->