Date | 3 May 2019 to 4 October 2019
(Closure A – existing closure which will be extended until 4 October 2019) 29 June 2019 to 4 September 2019 (Closure B) |
Day | Monday to Saturday |
Time | 9:00 a.m. to 6:00 p.m. and 11:00 p.m. to 5:00 a.m. |
Reason |
Closure A (existing closure): To facilitate utilities relocation and road widening works for the LRT3 project. Closure B: To facilitate road widening activities near the pond and Jalan Plumbum 7/102 junction for the LRT3 project. |
The closures and diversions are shown on the map below:
We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.
For more information, please contact:
Firdaus Dahari, Construction Manager : 019-3598002
Alia Amira Zulkhairi, PR & Stakeholder Management : 012-8298255