Traffic Notice: Continuation of Full Road Closure and Traffic Diversions on Jalan Langat from 14 August 2020 to 30 August 2020

 

Date 14 August 2020 to 30 August 2020
Day Monday to Friday
Time 10:00 p.m. to 5:00 a.m.
Reason To facilitate ‘U-trough’ launching works for the LRT3 project

 

The closure and diversions are as shown on the map below:

 

 

 

 

Throughout the Recovery Movement Control Order (RMCO) period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction works activities.

 

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

 

For more information, please contact :

En. Nor Azri Omar, Project Director                                                                                                                        : 012 – 320 5736

En. Mohd Azizi Bin Abd Hamid, Senior Manager, PR & Stakeholder                                                    : 019 – 227 9767

-->
Translate »
Notis Trafik: Lanjutan Penutupan Jalan dan Lencongan Trafik di Jalan Langat dari 14 Ogos 2020 hingga 30 Ogos 2020
August 12, 2020
Traffic Announcement: Continuation of Lane Closuree and Traffic Diversion on Jalan Langat (Banting-bound) from 17 August 2020 to 23 August 2020
August 14, 2020