Traffic Notice: Road Closures and Traffic Diversions on Persiaran Kerjaya (in front of Politeknik Sultan Salahuddin Abdul Aziz Shah, Shah Alam & Subang/KL-bound) and Jalan Subang (Guthrie Highway-bound) from 14 December 2020 to 16 December 2020  

 

Date 14 December 2020 to 16 December 2020
Day Monday to Wednesday
Time 11:00 p.m. to 5:00 a.m.
Reason To facilitate U-Girder launching works.

 

The closures and traffic diversions are as shown on the map below:

 

 

The diversions are implemented following the approval from Petaling Public Works Department (JKR Petaling). Throughout the Conditional Movement Control Order (CMCO) period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

 

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding.

 

For more information, please contact:

WL Hoon, Project Manager                                                                                                                                          : 019-6223228

Hanita Harun, PR & Stakeholder Management Manager                                                                           : 013-5755667

-->
Translate »
Notis Trafik: Penutupan Jalan dan Lencongan Trafik di Persiaran Kerjaya (berhadapan Politeknik Sultan Salahuddin Abdul Aziz Shah, (arah Shah Alam & Subang/KL) dan Jalan Subang (arah Lebuhraya Guthrie) dari 14 Disember 2020 hingga 16 Disember 2020  
December 9, 2020
Traffic Announcement: Lane Closures and Traffic Diversions on Jalan Langat, Klang (Banting/Klang-Bound) from 14 December 2020 to 18 December 2020
December 10, 2020