Traffic Announcement: Traffic Diversion At Persiaran Kerjaya, Shah Alam From 23 September 2018 to 30 April 2019

Date   23 September 2018 to 30 April 2019
Time   24 hours daily
Duration   220 Days
Reason   To facilitate bored piling, pier cap and pier column construction works at Persiaran Kerjaya for LRT3 project.


SHAH ALAM, SELANGOR – 19 September, 2018:
MRCB George Kent Sdn Bhd (MRCBGK), the Project Delivery Partner (PDP) of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be traffic diversion at Persiaran Kerjaya heading towards Shah Alam and Subang/ Kuala Lumpur from 23 September 2018 to 30 April 2019.

The traffic diversion is to facilitate bored piling, pier cap and pier column construction works at the road median at the junction in front of Nawas Maju Restaurant and Politeknik Sultan Salahuddin Abdul Aziz Shah, Shah Alam.

During this time, motorists from Jalan Subang to Jalan Pegawai U1/33 and from Jalan Pegawai U1/33 to Subang/Kuala Lumpur will be diverted as indicated in the GREEN arrows in the map below:

 

We apologise for any inconvenience caused to the public.

For public enquiries, kindly contact the LRT3 hotline at 1 800 18 2585.

 

–ENDS–

 

For media enquiries, please contact:

 

Lim Siew May
Manager, PR & Communications
MRCB George Kent Sdn Bhd

03-5033 6857

siewmay.lim@mrcbgk.com

 

Hanita Harun
WPC Public Relation & Stakeholder Management

013-5755667

hanita@gbg.com.my

 

ABOUT MRCB GEORGE KENT (MRCB GK)

MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4th September 2015 as the Project Delivery Partner (PDP) of the Light Rail Transit 3 (LRT3).

MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest home-grown railway system specialist in Malaysia.

MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3)

The LRT3 envisages connecting 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, visit www.lrt3.com.my and follow @myLRT3

 

 

 

 

 

 

-->
Translate »
Traffic Announcement: Traffic Diversion On Part of Jalan Meru, Klang From 15 until 30 September 2018
September 14, 2018
Notis Trafik: Lencongaan Trafik Akan Dilaksanakan di Persiaran Kerjaya, Shah Alam Untuk Kerja-kerja Ujian Cerucuk, Pemasangan Tetopi Tiang Sambut dan Pembinaan Tiang dari 23 September 2018 hingga 30 April 2019
September 18, 2018